Project: Yarmouth Regional Hospital

Delmar Construction successfully completed several contracts during the redevelopement of the Yarmouth Regional Hospital. Starting back in 1999  these included  Hemodialysis Relocation, The excavation and Demolition  in the 1961 building , boiler room renovations, Delmar was the General Contractor on Phase II  which was the construction of the new building . After the new building was completed  there were renovations made  in the  Phyciatric  Ward , Ocean View  Clinic, MRI Clinic, Oncology and Wellness Center, Doctors offices , 2nd floor offices as well as ventalation  and brick repointing on the exterior of the building these contracts at the time cost nearly 14,000,000.00. This includes work that Delmar has done during the current year which includes renovations to the Operating rooms .

Client: Yarmouth Regional Hospital (2012)
Location: 60 Vancover Street Yarmouth
Date: Jun, 2012

View Galery